Business Standby Generators: 2025–2026 Market Report
Data centers are soaking up factory capacity and lead times are stretching. Our November 2026 report on commercial standby generators, with a free PDF.
By Steph Lane · · 8 min read
The short version
Data centers rewired the commercial generator market, and everyone else is feeling it. Generac's commercial and industrial segment grew 28% in Q3 2026, Caterpillar's power generation sales grew 30%, and Cummins Power Systems grew 15%. New large standby generators are quoted at 40 weeks and up, and some makers are quoting well over a year.
Key numbers
- +28%: Generac C&I segment sales in Q3 2026, to $553M.
- $78B: Caterpillar's record backlog, up 96% in a year.
- 40–45 weeks: Generac's large-generator lead time on its Q2 call, with some rivals quoting 70–80.
- $2B+: Generac's expectation for 2027 data center revenue.
This is GenTrak's own market report, and you can download the full report as a PDF to keep or share.
2025: steady, with a rocket strapped to the side
If you only looked at the 2025 headline numbers, the commercial side looked like a normal year. Generac's C&I product sales grew 5% for the full year to $1.46 billion. But look at the fourth quarter: C&I product sales were up about 10% to $400 million, and the company said it was mostly from data center customers. That was the first clear sign of what was coming.
Meanwhile the home side had a rough year because outages were low. The two markets were moving in opposite directions.
2026: the data center squeeze
Every big maker reported the same story in October and November. Generac's C&I segment sales rose 28% to $553 million in Q3, with more than $100 million from data center products in the quarter alone. The company expects nearly $500 million of data center revenue for 2026. It signed a long-term supply agreement with Amazon for backup generators (about $2.4 billion of initial deliveries across 2027 and 2028) and put its data center backlog at about $4.5 billion. It now expects data center revenue to well exceed $2 billion in 2027.
Caterpillar had its highest sales quarter ever. Power generation sales rose 30% to $3.42 billion, and total backlog hit a record $78 billion, up 96% from a year ago. Cummins Power Systems sales rose 15% to $2.3 billion at a 25.4% EBITDA margin.
Each company reports power generation differently, so these are the closest like-for-like lines each one discloses. Sources: Generac Q3 2026 10-Q, Caterpillar Q3 2026 results coverage, Cummins Q3 2026 release.
The makers are spending to keep up. Generac says it is working to triple its large-generator production capacity. Rehlko began distributing its new KD Series generators in early 2026 and announced a new assembly facility in Kenosha, Wisconsin. None of it shows up on a dealer's lot in a hurry, because engine plants take years, not months.
What that does to lead times
On Generac's Q2 call in July, the CEO said large generator lead times at Generac were 40 to 45 weeks, and that some competitors were quoting 70 to 80. One distributor's 2026 estimates for new standby diesel give you a sense of the shape: small units wait a few months, and the big frames wait about a year or more.
| Size | Typical lead time, 2026 |
|---|---|
| 25–400 kW | 12–26 weeks |
| 500–600 kW | 12–30 weeks |
| 750–1,000 kW | 12–39 weeks |
| 1,250–3,250 kW | 52–70 weeks |
One distributor's estimates (Global Power Supply), not manufacturer quotes. Your numbers depend on brand, voltage, enclosure and tier. Another dealer, Generator Source, says factory orders for 2,000 and 3,000 kW units are stretching into late 2027. Switchgear and transformers can add to the wait.
Why this matters to a small business: a 50 or 100 kW generator for a restaurant, clinic or small plant doesn't compete directly with a hyperscale campus. But it shares factories, engines and alternators with it, and when the big orders get priority, everyone feels the ripple.
Used and surplus: the pressure valve
When new gear is a year out, buyers look at what already exists. Generator Source, a used and surplus dealer, says factory orders for the largest units are stretching into late 2027, which pushes buyers toward machines that can ship now. That tends to firm up prices for low-hour units in popular sizes (roughly 500 kW to 2 MW), while older units with no records or rental history trade lower.
Used value depends on hours, age, maintenance records and whether the unit has been load tested. Ask for all of it, and have a licensed technician look over anything you buy. If you want a starting number for a specific unit, our Price a Gen tool gives an estimate from hours, age and condition.
What commercial generators cost
For stationary generators above about 100 kW, manufacturers mostly don't publish prices, so GenTrak estimates new, zero-hour value from manufacturer and dealer pricing. Those estimates are in our catalog. At the low end, price per kW is high because there's a fixed cost in the controls, enclosure and alternator. It flattens out once you get past 150 kW.
GenTrak estimated fair market value, genset only (no transfer switch, freight or installation). Accuracy about ±20–30%. Diesel: SD050, SD100, SD150, SD250, SD500, SDMD1000. Natural gas: SG050, SG100, SG150, SG250, SG500, SG1000.
Diesel and gas are within about 6% of each other at 50–150 kW. From 250 kW up, the gas units run roughly $50–80 more per kW.
Brand differences at 500 kW are small. Our estimates put the Generac SD500, the Cummins C500 D6e and the Kohler 500REOZJC within about 2% of each other, around $130,000 to $132,500, which tells you the real difference is availability, service coverage and spec, not sticker price.
At the light-commercial end, where some makers do publish prices, the spread is clearer:
| Size | Model | Price | Basis |
|---|---|---|---|
| 100 kW | Generac Protector RG10090C | $36,689 | MSRP |
| 100 kW | Kohler KG100R | $40,901 | MSRP |
| 100 kW | Briggs & Stratton 100kW NG | $43,139 | Dealer retail |
| 150 kW | Generac Protector RG15090C | $46,289 | MSRP |
| 150 kW | Kohler 150ERESC | $51,917 | MSRP |
| 150 kW | Briggs & Stratton 150kW NG | $59,232 | Dealer retail |
GenTrak catalog, Nov. 8, 2026. Generac and Kohler are manufacturer list; Briggs & Stratton are dealer retail, single-phase base. Generator only. Three-phase, enclosures, transfer switches and installation are extra.
Tariffs and why I don't expect price cuts
Caterpillar expects about $2.2 billion of tariff costs in 2026, not counting recoveries of IEEPA tariffs, and said about $600 million of that lands in the third quarter. It also reported favorable price realization. In February the Supreme Court ruled the IEEPA tariffs unlawful, but the Section 232 steel and aluminum tariffs are separate. Temporary changes effective June 8, 2026 lower the U.S.-metal-content threshold for the reduced 10% rate from 95% to 85% and run through the end of 2027. That is relief at the margin, not a rollback. When demand is this strong and the makers are booked, I'd plan around flat to rising prices.
A few other things I'm watching
- Natural gas. Our catalog lists about 180 gas-fueled commercial and industrial models if you want to compare them with diesel.
- Backup to on-site power. Caterpillar's Q3 filing coverage mentions an agreement for up to 2.1 GW of gas generator sets for data center prime power. The line between standby and primary power is getting blurry.
- Market size numbers. IMARC sizes the global data center generator market at $8.18 billion in 2025, while MarketsandMarkets has it at $8.57 billion in 2026 growing to $9.79 billion by 2031. Methods differ, so use them for direction.
- Backlog and 2027. Generac expects its quoted lead times to normalize in the first quarter of 2027 after finishing a plant move, and says 2027 data center revenue should well exceed $2 billion. Its own filing also flags cancellation rights in some data center contracts, so a big backlog isn't all firm.
If you run a business and need standby power
- Start the clock early. Request quotes with delivery dates, and ask if the quote holds price.
- Size it right. Use our business planner to add up your loads, then compare real models in our 713 commercial and industrial listings.
- Look at used and surplus if you can't wait, but ask for hours, service records and a load test.
- Plan for the rest of the system. Transfer switches, switchgear, permits, fuel and freight can set your schedule. Our freight estimator gives a ballpark to your ZIP.
Download the full report (PDF)
GenTrak doesn't sell, broker, quote or install generators, and nothing here is financial, legal or electrical advice. Prices labeled "GenTrak catalog" come from our November 2026 generator table (manufacturer list prices where published, otherwise our estimated fair market value, typically ±20–30% for industrial units). Third-party figures are attributed to their source and some are analyst or distributor estimates, which can differ by publisher. A licensed electrician or dealer should confirm sizing and quotes before you buy.
Sources
- Generac Q4 and Full-Year 2025 results
- Generac Q3 2026 Form 10-Q (SEC)
- What Generac said on its Q3 2026 call
- Generac Q2 2026 call highlights (Nasdaq)
- Cummins Q3 2026 results
- Caterpillar Q3 2026: highest sales quarter ever (Manufacturing Dive)
- Caterpillar Q3 2026 (Utility Dive)
- Caterpillar Q3 2026 Form 10-Q (SEC)
- Global Power Supply: generator lead times in 2026
- Generator Source: the 2026 energy crisis
- Rehlko: KD Series launch (Power Progress)
- Rehlko press releases
- IMARC: data center generator market
- MarketsandMarkets: data center generators market
- Foley Hoag: Supreme Court strikes down IEEPA tariffs
- Plante Moran: Section 232 update (June 2026)
GenTrak is a research tool, not an electrician, contractor or dealer. Prices and specs change, so confirm details with the seller or manufacturer. Talk to a licensed electrician before you buy, install or connect a generator.